Downsizing Bridge Technology
Franklin County, Ohio's First Cable Stay
Bridge
Mark D. Sherman, P.E., Franklin County
Engineers Office
David W. Jones, P.E., Jones-Stuckey Ltd., Inc.
Can an owner ever justify building a bridge that costs 50%
more than a standard bridge? As the environmental process becomes
far too cumbersome to justify working against it, the use of
longer span bridges may relieve the strain on the relationship
between engineer and environmentalist. The bridge engineer must
work outside his knowledge base to understand all ramifications
of replacing bridges in sensitive environments. The bridge engineer
needs to find solutions that shorten the project time, which
includes the environmental process. In Franklin County, the
Engineers Office used this theory to build its first cable stay
bridge.
The bridge replacement for Beach Road over Big Darby Creek
had several environmental issues to overcome:
- The existing bridge was an historic wrought iron truss
built in 1888. The single truss spans 175 ft. across the Big
Darby Creek. The State Historic Preservation Office requested
that the replacement structure relate to the historic nature
of the truss and be the same language in design as the truss
we were replacing. That is to say, it should be a single-span
structure with above-deck supports leaving the river channel
open and clear.
- The Big Darby Creek is both a State Scenic River and National
Scenic River. For its protection, a well organized local group
looks into any and all proposed work along the stream and
its tributary.
- Wetlands located near the river did not allow for a significant
modification to the roadway profile.
- The Big Darby Creek has no flood-control devices upstream
from the site, resulting in very high peak water levels during
storm events. The roadway profile would need to be raised
significantly in order to allow the 100-year discharge under
a conventional bridge.
A single span bridge addressed all of these issues and was
acceptable to all the opponents, but "Why a cable stay
bridge at this location?" While the initial cost is more
than an owner would normally spend on a bridge this size, several
cost saving factors made this type of bridge an a attractive
solution. First, we save the time and money that would be spent
on a lengthy environmental battle. Second, the site had shallow
bedrock that assisted in reducing the foundation cost. Third,
there was no skew on the bridge, which made the superstructure
geometry simple. Additionally, the overhead suspension system
allowed the superstructure to clear the 100 year flood, and
the precast nature of the girders, floor beams and deck panels
made for a relatively maintenance free bridge with a service
life in excess of 100 years. It became obvious to those involved
with the project that the two-tower (three span) cable stay
configuration met all of the criteria for this application.
The new bridge is scheduled for completion in the spring of
2001. It consists of drilled shaft foundations for the towers
and rock anchors for the end span tie-downs. The superstructure
consists of prestressed, segmented, post-tensioned concrete
edge girders, with prestressed, post-tensioned concrete floor
beams, supporting precast, stay-in-place deck panels. The deck
is cast-in-place with high performance concrete. The cables
of the bridge are actually high-strength steel rods that are
grouted into a 4-inch diameter HDPE tube. These bar cables are
anchored individually at the top of the towers and the bottom
of the edge girders. The towers are cast-in-place concrete supporting
a structural steel anchoring plate assembly, which is encased
in concrete after the cables are installed. To provide for thermal
movement of the deck and edge girders, the back-span edge girders
have a vertical link assembly that allows movement in the girder
while anchoring the cables vertically into the bedrock directly
below the link assembly.
The bridge was engineered by Jones-Stuckey Ltd., Inc. of Columbus
and is being constructed by C.J. Mahan Construction Company
of Grove City, Ohio. It was a unique solution to a very environmentally
sensitive site. With its beauty emanating from its structural
design, the bridge will serve the citizens of Franklin and Madison
Counties for a long time to come.
Back to the Top
|